Refurbishing firefighter accommodation while maintaining 24/7 emergency response operations
Fire Rescue Victoria engaged Ducon to refurbish and reconfigure the first-floor accommodation facilities at Brunswick Fire Station.
The project was undertaken to modernise the station’s living quarters, creating four new individual firefighter bedrooms, a reconfigured locker room, upgraded circulation areas and a new lounge.
As the station remained operational throughout the works, the project required careful staging, clear communication and a construction approach that protected emergency response capability at all times.
Ducon delivered the refurbishment within a live emergency services environment operating 24 hours a day. The works were carefully planned and staged to maintain safe access, operational building services and uninterrupted emergency response capability throughout construction.
The project scope included:
During construction, Fire Rescue Victoria issued revised architectural and structural designs that significantly changed the approved scope of works. These changes introduced additional demolition, structural steel, plastering, flooring, carpentry and painting works, impacting critical path activities including set out, demolition, propping and structural steel procurement.
Ducon responded by reviewing the revised documentation, resequencing the programme and progressing works in unaffected areas while updated design information was finalised. This helped minimise downtime, maintain productivity and reduce disruption to station personnel.
The completed project delivered modern, compliant and more functional accommodation facilities for Fire Rescue Victoria’s Brunswick Fire Station.
The upgraded bedrooms, locker room, circulation areas and lounge have improved privacy, comfort and amenity for firefighters, while supporting the operational needs of a 24/7 emergency services environment.
Through proactive programme management, collaborative design coordination and careful live-site staging, Ducon delivered the refurbishment while maintaining uninterrupted emergency response operations throughout construction.
$266,666.64
Nov 2025 - Mar 2026
Emergency Services - live operational environments
Brunswick