What mattered, what we did, what it achieved.
Failed basement wall and drainage rebuilt with the car park still taking traffic.
More about governmentThe car park stayed open. Adjacent roads stayed in use.
Traffic management, Temporary shoring, Night works and Environmental plan.
The rebuilt basement wall panels and new drainage were handed over for $400,000 over one month, on budget, with the car park and adjacent roads in use throughout and nil incidents recorded. Ducon was asked to complete further works within the facility.
Dandenong Market, Wall & Drainage, the full profile
The constraint, the control and the outcome, in one document.
Other jobs that kept working.
Get the document
Leave your details if you would like us to follow up, or skip the form and download now. No phone call unless you ask for one.
Thanks, your download is starting.