Frankston Hospital: 2 West Refurbishment

Refurbishment of a level 2 mental health unit delivered while the hospital stayed fully operational.

Program70 working days
LocationFrankston, VIC
Value$1M
ClientPeninsula Health
Healthcare

Built around care.

At Frankston's 2 West that meant refurbishing a mental health unit with public safety and infection control held as clinical priorities, while the ward kept running around the works.

More about healthcare
1
What mattered

A level 2 mental health unit needed demolition and refurbishment while the hospital remained fully operational, raising both public safety and infection control across every route the works touched.

2
What we did

Works were confined to vacated level 2 spaces so the sequence protected the parts of the unit still in clinical use, with public safety weighted as a clinical consideration and infection control maintained across the whole program, not just the demolition phase.

3
What it achieved

The refurbishment was delivered inside 70 working days with the mental health unit continuing to operate around it throughout.

Project profile

Frankston Hospital: 2 West Refurbishment, the full profile

The constraint, the control and the outcome, in one document.

Talk to us before the program is locked.

Four questions before anything starts: what can't stop while we're here, when we can actually be there, what we're working with, and what completed looks like to you.